Audrey Gas Field

From A Barrel Full
Revision as of 15:52, 24 June 2024 by Abarrelfull (talk | contribs)
Jump to navigation Jump to search

Summary Information

  • Operator: Centrica
  • Country: UK
  • Location: Southern North Sea
  • Production start: 1998
  • Partners:
  • Type: Gas
  • Estimated Reserves:
  • Production Volume:

Description

  • The field consists of two unmanned platforms, Audrey A & B
  • Audrey acts as the main gas processing and export hub for **Ann**, **Audrey**, **Alison** and **Annabel**
    • The Ann field is located in blocks 48/10a and 49/6a, approximately 40km North North-East of the Lincolnshire Offshore Gas Gathering System (LOGGS) complex.
    • Ann combines a protected manifold structure with capacity for 3 wells and a remote wellhead
    • The Alison field is located in block 49/11a
    • The Alison installation is a protected manifold structure with capacity for 3 wells.
  • Gas exported via the Lincolnshire Offshore Gas Gathering System (Loggs).

Contractors

  • **Heerema Marine Contractors:** Audrey platforms
  • **AMEC:** Topsides detailed engineering, procurement and platform modifications to facilitate the Annabel subsea completion

Ann Gas Field Development

  • **J P Kenny:** Jack-up installed drilling template, manifold and protection structure


History

  • 1966 - Ann field developed
  • 1987 - Field development approved
  • 1992 - Approval granted for Ann
  • 1994 - Ann field begins production
  • 1995 - Alison approval granted
  • 1998 - Centrica acquires a stake from Powergen
  • 2012 - Production ceased at the Ann field
  • 2018 - Approval granted for decommissioning

=== Geology

Links

  1. UK Oil and Gas Fields by Approval Date
  2. List Of Oil and Gas Production Platforms In The UK
  3. UK Oil and Gas Field Approved Decommissioning Programmes
  4. FoundOcean Subsea References
  5. J P Kenny Subsea References
  6. Centrica strikes offshore deal
  7. AMEC Wins North Sea Engineering Services Contract from Venture Production