Shanghai LNG Terminal
Revision as of 10:10, 7 February 2024 by Abarrelfull (talk | contribs)
Summary Information
- Ownership: Shanghai LNG (CNOOC)
 - Website: http://www.cnoocgas.com/
 - Location: Shanghai, China
 - Capacity: 3.0 million tons/annum
 - Status: In Operation
 
+++ Brief Description
- Shanghai LNG Terminal and Underwater Gas Transmission Project is composed of LNG berth, terminal and underwater gas pipeline project. The terminal will be built in phases with a total capacity of 6mtpa. The first phase is 3 mtpa, and it includes a berth that can accommodate 165000 cubic meters LNG tanker, two LNG tanks with storage capacity of 160000 cubic meters each, underwater gas pipeline and other related facilities.
 - Shanghai LNG overall project also includes gas-fired power plants and local distribution project. The terminal site is located on Zhongximentang Island of Shanghai International Shipping Center.
 
+++ Technical Details
- Storage capacity: Three (3) LNG storage tanks with a gross capacity of 165,000 m3
 - Unloading capacity:
 - Send out capacity:
 - Constructor:
- **IHI / CTCI consortium:** engineering, procurement and construction (EPC) contract
 
 
+++ History
- 2005 - CNOOC & Shenergy Group sign agreement To Develop Shanghai LNG Terminal
 - 2006 - IHI consortium received an engineering, procurement and construction (EPC) contract
 - 2006 - Supply contract with Petronas Signed
 - 2009 - LNG terminal begins operations
 
+++ Ongoing Projects/Project Status
- The first phase is in operation
 
+++ Suppliers / Customers
- Suppliers: Malaysia LNG Terminal
 - Customers:
 
+++ Other Information