York Gas Field
Revision as of 16:59, 24 August 2023 by Abarrelfull (talk | contribs) (Created page with "=== Summary Information === * Operator: Spirit energy  * Country: UK  * Location: Southern North Sea * Production start: 2013 * Partners: 100% * Type: Gas * Estimated Reserves...")
Summary Information
- Operator: Spirit energy
 - Country: UK
 - Location: Southern North Sea
 - Production start: 2013
 - Partners: 100%
 - Type: Gas
 - Estimated Reserves:
 - Production Volume:
 
Description
- The York platform is an unmanned facility with a tie back to Centrica’s Easington Gas Processing Terminal via a 34 km (21.25 miles) 16 inch pipeline.
 - The York Field Development will exploit gas reservoirs in the Southern North Sea of the UK Continental Shelf, approximately 35 kilometres North-East of Easington.
 
Contractors
- **Heerema:** EPCI (Engineering, Procurement, Construction and Installation) contract of the 2,750 tonnes York platform
 - **Saipem:** Pipeline installation
 - **FoundOcean:** Grouting
 
History
- 2001 - York Gas Field discovered by Amerada Hess
 - 2003 - Centrica acquired a 23% stake
 - 2009 - Centrica acquired an additional 67% stake from Hess
 - 2011 - Heerema awarded Centrica York platform contract
 - 2013 - First gas produced
 - 2017 - Spirit energy becomes the operator
 
Geology
Links
- List Of Oil and Gas Production Platforms In The UK
 - FoundOcean Subsea References
 - Saipem Europe Pipeline References
 - HFG awarded Centrica York platform contract
 - Centrica acquires additional 67 per cent share in North Sea gas development
 - North Sea Gas Success For Amerada Hess
 - Centrica Energy announces production has started from its York platform
 - Spirit Energy launched following completion of Centrica and Bayerngas Norge E&P joint venture