− | * The Tamar platform | + | * The Tamar platform is located in approximately 800 feet of water and designed to process 1.2 billion standard cubic feet of gas per day. |
+ | * The Tamar field is estimated to contain 8.4 trillion cubic feet of gas and produces through several subsea wells connected to the platform by 150 km long flow lines. * The single-lift topsides facility has four deck levels and weighs nearly 10,000 tons when completed. | ||
+ | * The Tamar expansion project will see the addition of a new pipeline in phase 1 and compression in phase 2 | ||
=== Contractors === | === Contractors === | ||
Line 18: | Line 20: | ||
** Mono ethylene glycol (MEG) reclamation unit | ** Mono ethylene glycol (MEG) reclamation unit | ||
** Engineering, manufacturing and delivery of a subsea controls distribution system, umbilical termination assemblies (UTA) and related equipment | ** Engineering, manufacturing and delivery of a subsea controls distribution system, umbilical termination assemblies (UTA) and related equipment | ||
+ | * Tamar Expansion Project | ||
+ | ** Allseas: | ||
=== History === | === History === | ||
Line 24: | Line 28: | ||
* 2013 - Natural Gas Begins to Flow from Tamar | * 2013 - Natural Gas Begins to Flow from Tamar | ||
* 2020 - Chevron acquires Noble Energy | * 2020 - Chevron acquires Noble Energy | ||
+ | * 2022 - FID for Tamar expansion project | ||
=== Geology === | === Geology === |
Revision as of 16:55, 21 March 2023
Summary Information
- Operator: Chevron
- Country: Israel
- Location: Levantine Basin, eastern Mediterranean
- Production start: 2013
- Partners: Noble, Delek
- Type: Gas
- Estimated Reserves: 8.4 trillion cubic feet of gas
- Production Volume:
Description
- The Tamar platform is located in approximately 800 feet of water and designed to process 1.2 billion standard cubic feet of gas per day.
- The Tamar field is estimated to contain 8.4 trillion cubic feet of gas and produces through several subsea wells connected to the platform by 150 km long flow lines. * The single-lift topsides facility has four deck levels and weighs nearly 10,000 tons when completed.
- The Tamar expansion project will see the addition of a new pipeline in phase 1 and compression in phase 2
Contractors
- **Alliance Engineering:** Detailed engineering and design services for the Tamar Platform Project, including topsides facilities and deck structure
- **Aker Solutions:**
- Supply of 240 kilometres of steel tube umbilicals
- Mono ethylene glycol (MEG) reclamation unit
- Engineering, manufacturing and delivery of a subsea controls distribution system, umbilical termination assemblies (UTA) and related equipment
- Tamar Expansion Project
- Allseas:
History
- 2009 - Gas discovered in the Tamar field
- 2012 - Agreement with Dalia Power Energies Ltd. for the Sale of Natural Gas from the field
- 2013 - Natural Gas Begins to Flow from Tamar
- 2020 - Chevron acquires Noble Energy
- 2022 - FID for Tamar expansion project
Geology
Links
- Noble Energy Announces Significant Natural Gas Discovery at Tamar Well Offshore Israel
- Alliance Engineering awarded detailed engineering and design contract for Noble Energy's Tamar Platform topsides
- Aker Solutions to supply subsea umbilicals to Noble Energy
- Aker Solutions to supply MEG reclamation unit to Noble Energy
- Aker Solutions wins another subsea contract with Noble Energy
- Agreement with Dalia Power Energies Ltd. for the Sale of Natural Gas
- Noble Energy Announces Execution of Gas Sales Agreement With Israel Electric Corporation
- Natural Gas Began to Flow from Tamar
- Chevron Announces Agreement to Acquire Noble Energy