* Capacity: 30 million tons/annum & 605,000 bbl/day
 
* Capacity: 30 million tons/annum & 605,000 bbl/day
 
* Nelson Complexity:
 
* Nelson Complexity:
* Project Stage:
+
* Project Stage: Under construction
 
* Expected Completion: 2025
 
* Expected Completion: 2025
 
* Budget:
 
* Budget:
Line 30: Line 30:
  
 
=== History ===
 
=== History ===
* 20
+
* 2019 - Final investment decision
 +
 
 
=== Other Information ===
 
=== Other Information ===
 
-
 
-
 +
 
=== Links ===
 
=== Links ===
 
# [https://abarrelfull.blogspot.com/2022/09/exxonmobil-advancing-singapore-resid.html ExxonMobil Advancing Singapore Resid Upgrade Project Towards 2025 Startup]
 
# [https://abarrelfull.blogspot.com/2022/09/exxonmobil-advancing-singapore-resid.html ExxonMobil Advancing Singapore Resid Upgrade Project Towards 2025 Startup]

Latest revision as of 09:49, 12 January 2023

Summary Information

  • Ownership: Exxon
  • Website: http://www.exxonmobil.com
  • Wiki Page: Exxon Singapore Refinery
  • Location: Jurong Island, Singapore
  • Capacity: 30 million tons/annum & 605,000 bbl/day
  • Nelson Complexity:
  • Project Stage: Under construction
  • Expected Completion: 2025
  • Budget:

The Project

  • Project Type:
  • Project Summary: add approximately 20,000 barrels per day of light, heavy and extra-heavy lubricant base stocks
  • Main Contractors
  • Licences

Refining Units

Terminal Capacity

  • Crude Oil:
  • Refined Products:

Crude Supply

-

Products Produced

  • It will add approximately 20,000 barrels per day of light, heavy and extra-heavy lubricant base stocks
  • Marine fuels which meet the International Maritime Organization’s 0.50 percent sulfur requirement

History

  • 2019 - Final investment decision

Other Information

-

Links

  1. ExxonMobil Advancing Singapore Resid Upgrade Project Towards 2025 Startup