Difference between revisions of "Delfin LNG Export Terminal Project"
		
		
		
		
		Jump to navigation
		Jump to search
		
Abarrelfull (talk | contribs)  (→Links)  | 
				Abarrelfull (talk | contribs)   | 
				||
| Line 18: | Line 18: | ||
=== Ongoing Projects/Project Status ===  | === Ongoing Projects/Project Status ===  | ||
| − | * Commissioning is expected in [[LNG Terminals to be Completed in   | + | * Commissioning is expected in [[LNG Terminals to be Completed in 2026 | 2026]]  | 
=== Suppliers / Customers ===  | === Suppliers / Customers ===  | ||
Revision as of 08:38, 18 August 2022
Contents
Summary Information
- Ownership: Delfin Midstream
 - Website: https://www.delfinmidstream.com/
 - Location: Gulf of Mexico
 - Capacity: 13.0 million tons/annum
 - Status: Planned
 
Brief Description
- The project is a modular offshore export facility that uses up to 4 standardised vessels
 - The Delfin LNG deepwater port will reuse and repurpose two existing offshore natural gas pipelines; the former U-T Operating System (UTOS) pipeline and the High Island Offshore System (HIOS) pipeline
 - New laterals will connect the FLNG vessels to the pipelines
 
Technical Details
- Storage capacity:
 - Constructor: Samsung Heavy Industries and Black & Veatch: FEED for vessel
 - Licensor: Black & Veatch
 
Ongoing Projects/Project Status
- Commissioning is expected in 2026
 
Suppliers / Customers
- Suppliers:
 - Customers:
 
History
- 2020 - FEED completed for LNG vessel
 
Other Information
- -