| − | * -  | + | * The project is a modular offshore export facility that uses up to 4 standardised vessels  | 
| + | * The Delfin LNG deepwater port will reuse and repurpose two existing offshore natural gas pipelines; the former U-T Operating System (UTOS) pipeline and the High Island Offshore System (HIOS) pipeline  | ||
=== Technical Details ===  | === Technical Details ===  | ||
Revision as of 12:42, 14 January 2022
Contents
Summary Information
- Ownership:
 - Website:
 - Location:
 - Capacity: million tons/annum
 - Status: (In Operation / Planned / Under Construction)
 
Brief Description
- The project is a modular offshore export facility that uses up to 4 standardised vessels
 - The Delfin LNG deepwater port will reuse and repurpose two existing offshore natural gas pipelines; the former U-T Operating System (UTOS) pipeline and the High Island Offshore System (HIOS) pipeline
 
Technical Details
- Storage capacity:
 - Constructor: Samsung Heavy Industries and Black & Veatch: FEED for vessel
 - Licensor: Black & Veatch
 
Ongoing Projects/Project Status
- Commissioning is expected in 202X
 
Suppliers / Customers
- Suppliers:
 - Customers:
 
History
- 2020 - FEED completed for LNG vessel
 