− | + | * Under construction | |
+ | * Commissioning is scheduled for [[LNG Terminal Projects to be Completed in 2023 | 2023]] | ||
=== Suppliers / Customers === | === Suppliers / Customers === |
Revision as of 13:52, 6 January 2022
Contents
Summary Information
- Ownership: HPCL LNG
- Website: https://www.hplng.in/
- Location: Chhara, Gujarat, India
- Capacity: 5.0 million tons/annum
- Status: Under construction
Brief Description
- An onshore regasification terminal
Technical Details
- Storage capacity: 2 tanks of 200,000 m3 each
- Unloading capacity:
- Send out capacity:
- Constructor:
- Toyo-India: EPC work on a turnkey basis, from engineering to construction and commissioning
- IHI Corporation & Afcons: Engineering and procurement of the entire LNG tank, mechanical construction of the tank and trial operation
Ongoing Projects/Project Status
- Under construction
- Commissioning is scheduled for 2023
Suppliers / Customers
- Suppliers:
- Customers:
History
- 2019 - Toyo-India awarded EPC contract
- 2021 - HPLC became 100% owner of the project
Other Information
-