Summary Information
+
=== Summary Information ===
  
 
Ownership: Gasum
 
Ownership: Gasum
Line 5: Line 5:
 
Location: Inga
 
Location: Inga
 
Capacity: million tons/annum
 
Capacity: million tons/annum
Status: Planned
+
Status: Cancelled
Brief Description
+
=== Brief Description ===
  
 
The project has been cancelled
 
The project has been cancelled
Line 12: Line 12:
 
Annual throughput 10-20 TWh/y.
 
Annual throughput 10-20 TWh/y.
 
The project includes the BalticConnector, a high pressure transmission pipeline connecting Estonian and Finnish gas transmission networks. Bi-directional flow. Pipeline diameter 500 mm, annual capacity 2 bcm/a.
 
The project includes the BalticConnector, a high pressure transmission pipeline connecting Estonian and Finnish gas transmission networks. Bi-directional flow. Pipeline diameter 500 mm, annual capacity 2 bcm/a.
Technical Details
+
=== Technical Details ===
  
 
Storage capacity: 300,000 m3
 
Storage capacity: 300,000 m3
 
Unloading capacity:
 
Unloading capacity:
 
Send out capacity: 10-14 million nm3/day
 
Send out capacity: 10-14 million nm3/day
Constructor:
+
=== Constructor: ===
 
Neste Jacobs: Project Management Office
 
Neste Jacobs: Project Management Office
 
Ongoing Projects/Project Status
 
Ongoing Projects/Project Status
  
 
Commissioning is expected in 2018
 
Commissioning is expected in 2018
Suppliers / Customers
+
=== Suppliers / Customers ===
  
 
Suppliers:
 
Suppliers:
 
Customers: The Finnish grid and also the Baltic states
 
Customers: The Finnish grid and also the Baltic states
History
+
=== History ===
  
 
2012 - Gasum launched EIA
 
2012 - Gasum launched EIA
 
2013 - Neste Jacobs awarded PMO contract
 
2013 - Neste Jacobs awarded PMO contract
 
2015 - Project cancelled due to lack of commercial feasibility
 
2015 - Project cancelled due to lack of commercial feasibility
Other Information
+
=== Other Information ===
  
 
-
 
-

Latest revision as of 09:38, 21 August 2020

Summary Information

Ownership: Gasum Website: http://www.gasum.com/ Location: Inga Capacity: million tons/annum Status: Cancelled

Brief Description

The project has been cancelled A Full scale LNG terminal project to the southern coast line of Finland. Storage capacity 300,000 m3 of LNG, injection capacity to the Finnish gas transmission network 10-14 million nm3/day. Annual throughput 10-20 TWh/y. The project includes the BalticConnector, a high pressure transmission pipeline connecting Estonian and Finnish gas transmission networks. Bi-directional flow. Pipeline diameter 500 mm, annual capacity 2 bcm/a.

Technical Details

Storage capacity: 300,000 m3 Unloading capacity: Send out capacity: 10-14 million nm3/day

Constructor:

Neste Jacobs: Project Management Office Ongoing Projects/Project Status

Commissioning is expected in 2018

Suppliers / Customers

Suppliers: Customers: The Finnish grid and also the Baltic states

History

2012 - Gasum launched EIA 2013 - Neste Jacobs awarded PMO contract 2015 - Project cancelled due to lack of commercial feasibility

Other Information

-

Links

  1. Liquefied natural gas (LNG) import terminal for Southern Finland planned by Gasum
  2. Neste Jacobs wins the bidding competition of Gasum's Finngulf LNG Project Management Services
  3. Finngulf terminal and Balticconnector pipeline not commercially viable