Abarrelfull (talk | contribs)  (Created page with "Summary Information * Operator: RWE * Country: UK * Location: 140 km north-east of Easington on the Lincolnshire coast and 180 km north of Bacton on the Norfolk coast * Produc...")  | 
				Abarrelfull (talk | contribs)   | 
				||
| Line 18: | Line 18: | ||
* **Seaway Heavy Lifting:** Installation of Minimum Facility Platform  | * **Seaway Heavy Lifting:** Installation of Minimum Facility Platform  | ||
* **Micoperi:**    | * **Micoperi:**    | ||
| − | + | ** Installation of subsea pipeline 10” plus 3” piggy back 45 km long  | |
| − | + | ** Cavendish Platform Installation    | |
+++ History  | +++ History  | ||
Revision as of 14:32, 27 April 2023
Summary Information
- Operator: RWE
 - Country: UK
 - Location: 140 km north-east of Easington on the Lincolnshire coast and 180 km north of Bacton on the Norfolk coast
 - Production start: 2007
 - Partners: RWE - 50%, Dana Petroleum 50%,
 - Type: Gas
 - Estimated Reserves:
 - Production Volume: initial production rates of 1,6 million m3
 
+++ Description
- The Cavendish field was discovered in 1989 and development sanction was granted in 2005. The development consists of a 6-slot minimum facilities fixed platform which is tied back to the Murdoch platform, part of the Caister Murdoch System operated by ConocoPhillips, via 47 kms of newly laid pipeline.
 - Gas is then transported onward to the Theddlethorpe Gas Terminal in the UK.
 
+++ Contractors
- **Technip:** Pipelay contract for the 48 km export pipeline from the Cavendish Field to the Murdoch facilities
 - **Heerema:** Contract to engineer, procure and construct (EPC) a NUI (normally unmanned installation)
 - **Seaway Heavy Lifting:** Installation of Minimum Facility Platform
 - **Micoperi:**
- Installation of subsea pipeline 10” plus 3” piggy back 45 km long
 - Cavendish Platform Installation
 
 
+++ History
- 1989 - The Cavendish field was discovered
 - 2005 - Development sanction was granted
 - 2006 - Pipelay contract awarded to Technip
 - 2007 - First gas produced
 
+++ Geology
+++ Links
- Micoperi Offshore And Platform References
 - Micoperi Offshore Pipeline References
 - Seaway Heavy Lifting Oil And Gas References
 - Cavendish Gas Field Begins Production
 - RWE, UK Activities
 - Cavendish Field Development: Pipelay contract awarded to Technip Offshore UK Ltd
 - Heerema Vlissingen awarded the Cavendish Platform contract
 - RWE Dea UK receives development go ahead for Cavendish gas field in the UK Southern North Sea