=== Brief Description ===  | === Brief Description ===  | ||
* An onshore, mid sized LNG liquefaction plant that will be built in 2 phases  | * An onshore, mid sized LNG liquefaction plant that will be built in 2 phases  | ||
| + | * The marine loading facility, to be located along Belle Pass, will consist of both a single ship berth and a maneuvering basin.  | ||
=== Technical Details ===  | === Technical Details ===  | ||
| − | * Storage capacity:  | + | * Storage capacity: 2x 88,000 m3 tanks  | 
* Constructor:  | * Constructor:  | ||
* Licensor:  | * Licensor:  | ||
| Line 21: | Line 22: | ||
=== Suppliers / Customers ===  | === Suppliers / Customers ===  | ||
| − | * Suppliers:    | + | * Suppliers: Natural gas delivery to the site will occur through a short pipeline spur that will consist of a pipeline built to run approximately 600 yards to the west of the Fourchon LNG Facility. The pipeline will connect to an existing pipeline, the [[Kinetica Energy Express Gas Pipeline System]]  | 
| − | * Customers:    | + | * Customers:  | 
=== History ===  | === History ===  | ||
| − | * -  | + | * 2018 - Project FERC authorisation for FTA and non FTA export  | 
=== Other Information ===  | === Other Information ===  | ||
| Line 32: | Line 33: | ||
=== Links ===  | === Links ===  | ||
# [https://www.energy.gov/sites/prod/files/2018/03/f49/ord4162.pdf FERC Authourisation]  | # [https://www.energy.gov/sites/prod/files/2018/03/f49/ord4162.pdf FERC Authourisation]  | ||
| + | # [[Long Term Applications Received by DOE/FE]]  | ||
[[category:LNG]]  | [[category:LNG]]  | ||
[[category:USA]]  | [[category:USA]]  | ||
Latest revision as of 07:29, 14 February 2024
Contents
Summary Information
- Ownership: Fourchon LNG
 - Website: http://fourchonlng.net/
 - Location: Port Fourchon, Lafourche Parish, Louisiana
 - Capacity:
- Phase I: 2.0 million tons/annum
 - Phase II: 5.0 million tons/annum
 
 - Status: Planned
 
Brief Description
- An onshore, mid sized LNG liquefaction plant that will be built in 2 phases
 - The marine loading facility, to be located along Belle Pass, will consist of both a single ship berth and a maneuvering basin.
 
Technical Details
- Storage capacity: 2x 88,000 m3 tanks
 - Constructor:
 - Licensor:
 
Ongoing Projects/Project Status
- Commissioning is expected in 202X
 
Suppliers / Customers
- Suppliers: Natural gas delivery to the site will occur through a short pipeline spur that will consist of a pipeline built to run approximately 600 yards to the west of the Fourchon LNG Facility. The pipeline will connect to an existing pipeline, the Kinetica Energy Express Gas Pipeline System
 - Customers:
 
History
- 2018 - Project FERC authorisation for FTA and non FTA export
 
Other Information
- -