=== Summary Information ===  | === Summary Information ===  | ||
| − | * Ownership:    | + | * Ownership: Guangdong Huizhou LNG  | 
* Website:    | * Website:    | ||
* Location:    | * Location:    | ||
| Line 19: | Line 19: | ||
=== Ongoing Projects/Project Status ===  | === Ongoing Projects/Project Status ===  | ||
| − | + | * Commissioning is expected in [[LNG Terminal Projects to be Completed in 2024 | 2024]]  | |
=== Suppliers / Customers ===  | === Suppliers / Customers ===  | ||
Latest revision as of 16:49, 6 January 2022
Contents
Summary Information
- Ownership: Guangdong Huizhou LNG
 - Website:
 - Location:
 - Capacity: 6.2 million tons/annum
 - Status: Under construction
 
Brief Description
- In the first phase of the project will include the construction of a jetty and three LNG storage tanks of a 200 000 m3 capacity each and will have a regasification capacity of 6.2 MTPA.
 
Technical Details
- Storage capacity: 3x 200,000 m3 tanks
 - Unloading capacity:
 - Send out capacity:
 - Constructor:
- TGE:EPC for three 200,000 m3 prestressed full containment LNG tanks
 
 
Ongoing Projects/Project Status
- Commissioning is expected in 2024
 
Suppliers / Customers
- Suppliers:
 - Customers:
 
History
- 2021 - Construction of the project started
 
Other Information
-