* The development consists of four fields, Cravo, Lirio, Orquidea and Violeta  | * The development consists of four fields, Cravo, Lirio, Orquidea and Violeta  | ||
* These fields are located in Block 17 offshore Angola in water depths of 1,100 to 1,400 m  | * These fields are located in Block 17 offshore Angola in water depths of 1,100 to 1,400 m  | ||
| − | * The project comprises 34 wells and 8 manifolds connected by 180 km of subsea pipelines to the [[  | + | * The project comprises 34 wells and 8 manifolds connected by 180 km of subsea pipelines to the [[CLOV FPSO]] unit  | 
| − | * The gas produced on CLOV will be exported via a subsea line to the onshore   | + | * The gas produced on CLOV will be exported via a subsea line to the onshore [[Angola Soyo LNG Terminal]] liquefaction plant  | 
| + | * '''Begonia''' The Begonia Project will collect oil and gas from the reservoir, via a subsea-to-subsea tie-back to the existing FPSO  | ||
=== Contractors ===  | === Contractors ===  | ||
| Line 28: | Line 29: | ||
* **JDR Cable Systems:** Design, manufacture and testing of 9 umbilical and reeler systems  | * **JDR Cable Systems:** Design, manufacture and testing of 9 umbilical and reeler systems  | ||
* **KWsubsea:** Lateral buckling and pipeline walking assessment and mitigation design for  pipeline systems  | * **KWsubsea:** Lateral buckling and pipeline walking assessment and mitigation design for  pipeline systems  | ||
| + | |||
| + | ==== Begonia ====  | ||
| + | * McDermott: Engineering, procurement, supply, construction, installation, pre-commissioning and assistance to commissioning and start-up (EPSCI)  | ||
===  History ===  | ===  History ===  | ||
| Line 36: | Line 40: | ||
* 2014 - CLOV begins production  | * 2014 - CLOV begins production  | ||
* 2021 - Phase 2 begins production  | * 2021 - Phase 2 begins production  | ||
| + | * 2022 - FID for Begonia project  | ||
=== Geology ===  | === Geology ===  | ||
| Line 44: | Line 49: | ||
# [[Serimax Pipeline References]]  | # [[Serimax Pipeline References]]  | ||
# [[KWsubsea Deepwater Project Highlights References]]  | # [[KWsubsea Deepwater Project Highlights References]]  | ||
| + | # [[KWSubsea Lateral Buckling and Pipeline Walking References]]  | ||
# [http://killajoules.wikidot.com/archive:acergy-s-a-awarded-1-3-billion-contract-for-deepwate Acergy S.A. awarded $1.3 billion contract for deepwater development offshore West Africa]  | # [http://killajoules.wikidot.com/archive:acergy-s-a-awarded-1-3-billion-contract-for-deepwate Acergy S.A. awarded $1.3 billion contract for deepwater development offshore West Africa]  | ||
# [http://killajoules.wikidot.com/archive:angola:total-launches-clov-development-on-block-17 Angola: Total Launches CLOV Development on Block 17]  | # [http://killajoules.wikidot.com/archive:angola:total-launches-clov-development-on-block-17 Angola: Total Launches CLOV Development on Block 17]  | ||
| Line 54: | Line 60: | ||
# [http://killajoules.wikidot.com/blog:5617 Inauguration of CLOV in Angola]  | # [http://killajoules.wikidot.com/blog:5617 Inauguration of CLOV in Angola]  | ||
# [https://a-barrel-full.blogspot.com/2021/12/start-up-of-clov-phase-2-project.html Start-up of CLOV Phase 2 project]  | # [https://a-barrel-full.blogspot.com/2021/12/start-up-of-clov-phase-2-project.html Start-up of CLOV Phase 2 project]  | ||
| + | # [https://a-barrel-full.blogspot.com/2022/09/mcdermott-selected-for-begonia-project.html McDermott Selected for Begonia Project by TotalEnergies EP Angola Block]  | ||
Latest revision as of 17:20, 28 December 2024
Contents
Summary Information
- Operator: Total
 - Country: Angola
 - Location: Block 17
 - Production start: 2014
 - Partners: Total - 40%, Statoil (23.33%), Esso (Block 17) Limited (20%) and BP (16.67%).
 - Type: Oil & Gas
 - Estimated Reserves: The proved and probable reserves are estimated at approximately 500 million barrels of oil
 - Production Volume:
 
Description
- The development consists of four fields, Cravo, Lirio, Orquidea and Violeta
 - These fields are located in Block 17 offshore Angola in water depths of 1,100 to 1,400 m
 - The project comprises 34 wells and 8 manifolds connected by 180 km of subsea pipelines to the CLOV FPSO unit
 - The gas produced on CLOV will be exported via a subsea line to the onshore Angola Soyo LNG Terminal liquefaction plant
 - Begonia The Begonia Project will collect oil and gas from the reservoir, via a subsea-to-subsea tie-back to the existing FPSO
 
Contractors
Phase 1
- Daewoo Shipbuilding & Marine Eng. Co. Ltd. (DSME): Engineering, procurement, installation and construction of FPSO
 - **KBR:** Detailed design of topsides
 - **Technip:** 76 kilometers of dynamic and static production and water injection umbilicals
 - **Subsea 7:** Engineering, procurement, fabrication and installation of 130km of pipes
 - **FMC Technologies:**
- Fabrication, assembly and testing of 36 wellhead systems and 19 subsea trees
 - Manufacture of 7 complete manifold systems
 - Critical equipment testing, offshore installation support and equipment refurbishment
 
 - **Vallourec:** Supply of 28,500 tons - or 200 km - of coated seamless line pipes and bends
 - **JDR Cable Systems:** Design, manufacture and testing of 9 umbilical and reeler systems
 - **KWsubsea:** Lateral buckling and pipeline walking assessment and mitigation design for pipeline systems
 
Begonia
- McDermott: Engineering, procurement, supply, construction, installation, pre-commissioning and assistance to commissioning and start-up (EPSCI)
 
History
- 2010 - FMC awarded subsea production equipment contract
 - 2010 - KBR awarded topsides contract
 - 2011 - Technip awarded umbilical contracts
 - 2013 - The FPSO arrived in Angola
 - 2014 - CLOV begins production
 - 2021 - Phase 2 begins production
 - 2022 - FID for Begonia project
 
Geology
- The development will produce two types of oil: one with a 32 to 35° API gravity from the Oligocene reservoirs (Cravo-Lirio) and the other, more viscous, with a 20 to 30° API gravity from the Miocene reservoirs (Orquidea-Violeta)
 
Links
- Saipem Africa Pipeline References
 - Serimax Pipeline References
 - KWsubsea Deepwater Project Highlights References
 - KWSubsea Lateral Buckling and Pipeline Walking References
 - Acergy S.A. awarded $1.3 billion contract for deepwater development offshore West Africa
 - Angola: Total Launches CLOV Development on Block 17
 - FMC Technologies Awarded $520 Million Order for Total's CLOV Development
 - JDR To Supply FMC With (IWOC) Umbilical And Reeler Systems For The CLOV Project
 - KBR to Execute Topsides Detailed Design for TOTAL's CLOV FPSO
 - Technip awarded umbilical contracts in Angola
 - Vallourec provides Total with a wide range of premium offshore solutions off the Angolan coast
 - CLOV Start Up In Angola: Total Increases Block 17 Production To 700,000 Barrels Per Day
 - Inauguration of CLOV in Angola
 - Start-up of CLOV Phase 2 project
 - McDermott Selected for Begonia Project by TotalEnergies EP Angola Block