Difference between revisions of "Kazakhstan IPCI Petrochemical Project"

From A Barrel Full
Jump to navigation Jump to search
Line 19: Line 19:
 
* 2017 – Groundbreaking ceremony
 
* 2017 – Groundbreaking ceremony
 
* 2020 - Major equipment installed
 
* 2020 - Major equipment installed
 +
* 2022 - KMG acquired 49.5% from Samruk-Kazyna JSC
 
* 2022 - Production starts
 
* 2022 - Production starts
  
Line 27: Line 28:
 
# [https://abarrelfull.blogspot.com/2020/10/the-groundbreaking-ceremony-of-ipci.html The Groundbreaking Ceremony of IPCI project in Kazakhstan]
 
# [https://abarrelfull.blogspot.com/2020/10/the-groundbreaking-ceremony-of-ipci.html The Groundbreaking Ceremony of IPCI project in Kazakhstan]
 
# [https://abarrelfull.blogspot.com/2020/10/propane-propylene-splitter-of-pdh-plant.html Propane-propylene splitter of the PDH Plant in Kazakhstan IPCI Project Successfully Lifted in Place]
 
# [https://abarrelfull.blogspot.com/2020/10/propane-propylene-splitter-of-pdh-plant.html Propane-propylene splitter of the PDH Plant in Kazakhstan IPCI Project Successfully Lifted in Place]
 +
# [https://abarrelfull.blogspot.com/2024/01/transaction-completed-on-acquisition-of.html Transaction Completed on Acquisition of Interest in Kazakhstan Petrochemical Industries Inc.]
 
# [https://abarrelfull.blogspot.com/2023/10/president-launches-gas-chemical-complex.html President Launches Gas Chemical Complex in Atyrau Region]
 
# [https://abarrelfull.blogspot.com/2023/10/president-launches-gas-chemical-complex.html President Launches Gas Chemical Complex in Atyrau Region]
  

Revision as of 11:45, 8 January 2024

Summary Information

  • Owner: KPI (Kazakhstan Petrochemical Industries)
  • Website: https://www.kpi.kz/en/
  • Location: Aytaru, Kazakhstan
  • Completion: 2022

Project Details

  • The first phase of the complex involves a 500 ktpa propylene plant and a 500 ktpa polypropylene plant. The PDH unit uses CB&I's CATOFIN® propane dehydrogenation technology, and the polypropylene plant uses CB&I's Novolen® advanced gas-phase polypropylene technology.
  • Propane is supplied from the Tengiz Oil Field

Contractors

  • Hualu Engineering & Technology Co: Construction
  • CB&I: process licences


History

  • 2013 – Petrofac consortium awarded EPC contract
  • 2017 – CB&I awarded process licences
  • 2017 – Groundbreaking ceremony
  • 2020 - Major equipment installed
  • 2022 - KMG acquired 49.5% from Samruk-Kazyna JSC
  • 2022 - Production starts


Links

  1. Petrofac Consortium Appointed by KLPE LLP (KLPE) for Integrated Petrochemical Project in Kazakhstan
  2. CB&I Receives Full Notice to Proceed for Petrochemical Plant in Kazakhstan
  3. The Groundbreaking Ceremony of IPCI project in Kazakhstan
  4. Propane-propylene splitter of the PDH Plant in Kazakhstan IPCI Project Successfully Lifted in Place
  5. Transaction Completed on Acquisition of Interest in Kazakhstan Petrochemical Industries Inc.
  6. President Launches Gas Chemical Complex in Atyrau Region