| Line 24: | Line 24: | ||
=== Projects ===  | === Projects ===  | ||
* A 25,000 bpd Alkylation unit is being constructed. Completion is planned for 2020  | * A 25,000 bpd Alkylation unit is being constructed. Completion is planned for 2020  | ||
| − | * See [[St Charles Refinery Upgrade Project]]  | + | * The refinery was upgraded with the addition of a Hydrocracker in 2013  | 
| − | + | ** See [[St Charles Refinery Upgrade Project]]  | |
| + | |||
=== Other Information ===  | === Other Information ===  | ||
-  | -  | ||
Revision as of 10:19, 11 March 2020
Contents
Summary Information
- Ownership: Valero
 - Website: http://www.valero.com/
 - Location: St. Charles, New Orleans, Louisiana, USA
 - Capacity: 12.5 million tons/annum & 250,000 bbl/day
 - Nelson Complexity:
 - Refining Depth:
 
Brief Description
- A large complex refinery
 
Refining Units
- Atmospheric Distillation
 - delayed coker - 60,000-BPD
 - alkylation unit - 13,000-BPD
 - fluid catalytic cracking unit (FCCU) that includes a flue-gas scrubber - 90,000-BPD
 - continuous catalytic regenerating (CCR) reformer - 25,000-BPD
 
Terminal Capacity
- Crude Oil:
 - Refined Products:
 
Crude Supply
- Access to the Louisiana Offshore Oil Port (LOOP) where it can receive crude oil through pipeline or from five marine docks along the Mississippi River
 
Products Produced
- Gasoline, distillates and other light products represent approximately 80 percent
 - Products can be distributed via the Colonial Oil Products Pipeline, Bengal Oil Products Pipeline and Plantation Oil Products Pipeline
 
Projects
- A 25,000 bpd Alkylation unit is being constructed. Completion is planned for 2020
 - The refinery was upgraded with the addition of a Hydrocracker in 2013
 
Other Information
-
History
- 2002 - Continuous catalytic regenerating (CCR) reformer commissioned
 - 2003 - Acquired by Valero with the purchase of Orion
 - 2008 - Fluor awarded engineering, procurement, construction and construction management services contract, for upgrade project
 - 2011 - Air Products announces contract to Supply Additional Hydrogen following the upgrade
 - 2018 - Alkylation project started